New construction for Delacon Biotech

Facts and Figures
Company IAT GmbH
Principal Porr Bau GmbH
Location Engerwitzdorf - Austria
Type Waterproofing
Contract duration 06.2019 - 03.2020
Service duration 06.2019 - 03.2020
Runtime 06.2019 - 03.2020

New construction for Delacon Biotech

The new company location consists of an office building, laboratory and a production hall and warehouse.

A total roof area of approx. 4,200m² was sealed.

Flat roof office + laboratory building: approx. 1,000m² green roof (extensive)

Composition: concrete ceiling

             Undercoat (Büsscher&Hoffmann)

             Vapour control layer (Büsscher&Hoffmann)

             EPS-W-25 Heat insulating panel

             1st layer KVEW55K (Büsscher&Hoffmann)

             2nd layer KVEW55K (Büsscher&Hoffmann)

             XPSG30S

             Fleece 200g/m²

             Drain and water storage element

             Extensive substrate

             Hydroseeding

Flat roof production hall and warehouse: approx. 3,200m² gravel roof

Composition: trapezoidal sheet

              Undercoat (Büsscher&Hoffmann)

              Vapour control layer (Büsscher&Hoffmann)

              EPS-W-25 Heat insulating panel

              1st layer GGE40PS classic (Büsscher&Hoffmann)

              2nd layer KVDE55K (Büsscher&Hoffman)

              6cm gravel 16/32